Physics Of Medicine
A project where 2no Chillers were replaced with new state-of-the-art Climaventa Chillers which include free cooling technology. CPS carried out the complete mechanical & Electrical elements on the project, these consisted of a temporary chiller installation to ensure the building continued to function while the works were carried out. New chillers, primary and secondary pumps, and replacement pipework from chillers. BMS control modifications and new mains power supplies have been installed to accommodate the new electrical requirements. All the CHWS is now metered to give an accurate usage calculation on each individual circuit. This facility now has a 4000L buffer vessel which will supply reliable cooling capacity which is extremely important for the function of the building